The aim of this report is to describe the preparatory activities including modifications performed to the SPIDER Beam Dump (SDB) before the installation of the component on the vessel front lid. These modifications have been implemented to fix issues discovered on site checking the interfaces. Then, the Beam Dump installation of the vessel has been executed as documented in the second part of this document. Finally, data for the procurement of spare cooling bellows are provided.

Keywords

NBTF, neutral beam test facility, SPIDER, SPIDER beam dump

CNR authors

Cervaro Vannino, Fincato Michele, Grando Luca, Dalla Palma Mauro, Rossetto Federico, Degli Agostini Fabio, Pasqualotto Roberto

CNR institutes

IGI – Istituto gas ionizzati, ISTP – Istituto per la Scienza e Tecnologia dei Plasmi