Rapporto di progetto (Project report), 2019, ENG

On-site Assembly, Installation, and Acceptance Test Plan of SPIDER Beam Dump

Dalla Palma M.; Brombin M.; Tollin M.; Zaupa M.

Consorzio RFX (CNR, ENEA, INFN, Università di Padova, Acciaierie Venete SpA), Corso Stati Uniti 4 - 35127 Padova, Italy.

The preliminary assembly plan prepared by ITER Organization [R1] describes the SBD interfaces, but it requires to be integrated by another document as lifting, drawing up, and positioning have to be carried out by using a lifting jig. Existing documents regarding SBD handling and installation have been analysed and remaining issues have been addressed as described in the present document. The on-site acceptance test plan has been developed considering component characteristics, installed sensors, and analysed risks [A1].

Keywords

NBTF, neutral beam test facility, SPIDER, SPIDER Assembly

CNR authors

Brombin Matteo, Dalla Palma Mauro

CNR institutes

ISTP – Istituto per la Scienza e Tecnologia dei Plasmi

ID: 408702

Year: 2019

Type: Rapporto di progetto (Project report)

Creation: 2019-10-31 14:18:00.000

Last update: 2023-06-30 13:15:20.000

External IDs

CNR OAI-PMH: oai:it.cnr:prodotti:408702